Building R.Shea Brewing: Week 18, Dec 1-7, 2014
Building a Brewery
Building R.Shea Brewing: Week 18, Dec 1-7, 2014
Dec 11, 2014
As I write this, my body is sore from the night before's work. We are getting there on the renovations. Making progress...still one step forward, two steps back.
Bathroom Facelift
Back in the first month we took out about 100 pieces of red/clay ceramic tile from the main area. I didn't plan on saving them but they mostly came up unbroken so I wanted to reuse them. I know that I needed to do something with the bathroom floors.
Now, from when we removed ceramic tile from layers of vinyl tile months ago we found out that ceramic tile sticks exceptionally well to vinyl tile. I 'was' going to just put this reclaimed ceramic tile on top of this vinyl - just to save time. But I just couldn't. If I'm going to do something, let's do them the right way.
No More Christmas
The Christmas Ale came and went so fast I barely had any myself! This year's recipe really came together nicely and was different than other Christmas beers. People loved it. Too bad I can't make more but I'm transitioning to the brewery now. I may make this again early January on the pilot system, but at the new brewery
Next Week
- Receive on demand water heater.
- Receive brewery plumbing (it was delayed a little)
- Start work tiling the wall behind the brewery.
Thanks!
Much thanks to Jesse this week. We brewed Sunday and I asked if he could come over a few days later to remove bathroom tile. His work helped this job go super quick.
-
The Journey
- Building R.Shea Brewing: Week 17, Nov 24-30, 2014 (previous post)
- Building R.Shea Brewing: Week 19, Dec 8-14, 2014 (next post)