Building R.Shea Brewing: Week 15, Nov 10-16, 2014
Building a Brewery
Building R.Shea Brewing: Week 15, Nov 10-16, 2014
Nov 20, 2014
The Brew System Arrives!
After sitting for nearly nine months in my garage - cold, dark and lonely, I finally got the 3.5 barrel brew system moved out to it's real home. Why have I had it so long? Right now, the lead times on a system are three to five months as there is no inventory since the industry is on fire and demand is outstripping supply. When I ordered it late Fall of 2013, it was because 'when' I found a place, I didn't want this to cause delays. Due to the long waiting period since this system was made to when I will actually make beer out of it, the beer will be exceptional as these tanks are thinking, "It's about time we're serving our purpose! We're going to make some darn good beer for this place."
At the brewery, since the floors are done, security system installed, the fermentors in, this was the last item to get moved.
This system features jacketed/insulated tanks. It cost more but it will be well worth it as far as heat-up times, even temperature gradients and overall safety.
Why a 3.5 bbl Brew System?
That question is one that I have spent a lot of time on a spreadsheet with and running endless calculations. There is an overwhelming amount of anecdotal and written evidence that when most brewers start with anything less, even down to a homebrew 1/2 barrel system, that it is a rough time and a lot of work (A LOT) assuming you are successful. Anything smaller than a 3.5 barrel will not allow you to produce enough to make much, if not any re-investment to a larger system. Of course there are brewers that HAVE made it on a smaller system and have eventually upgraded but these are the outliers. If you are successful on a smaller scale you are brewing nearly every day, if not multiple times a day...cleaning kegs daily, etc. *The above does assume some kegging and bottling for distribution. If you JUST have a taproom, it is easier on a smaller scale, though a lot more limiting. Since brewing on my pilot system for the last three years, I wanted to do this smartly...don't work harder, work smarter...have a system that can fully run a taproom and also provide enough for bottling and limited kegging for others.
I have also read countless people writing on forums that they upgraded six months in. Why put all the work in upfront to only redo it in a short amount of time?
A 3.5 barrel system will be able to crank out a lot of beer. The limiting factor is the fermentors. I can always add more fermentors for more production. I can even add larger fermentors (maybe 4-5 barrel) and still use the current building. Brewing twice a day to fill a fermentor is not a problem, or to fill it on successive days even. 3.5 barrels equates to six kegs - it offers enough for a busy taproom and some leftover for distribution and will pay the bills while providing some room from growth which would have to be another building.
Plus 3.5 barrels is the 'sweet spot' size for ample production for a taproom AND the equipment is 'just' small enough to fit in a large door and can be moved around with a few guys. Anything bigger and you have to start talking about steam heating and boilers, and needing a forklift to move anything...and able to get it inside. Also that would involve a large expense to retrofit a building for larger equipment as most glycol systems will now require 220 voltage, bigger plumbing, etc. Also, the cost of a bigger brewing system starts to skyrocket after three barrels. I wanted to keep my expenses down, with a system just big enough to put out a lot of beer that didn't cost me an arm and a leg in terms of a loan. The last thing I want to do is leverage my family in this endeavor. I like to play it safe financially and mitigate risk.
At the end of the day, if R.Shea Brewing works and y'all like my beer, it's big enough to handle the volume off the bat and I will still have time to come home to see my family and sleep. If it doesn't work (though it's gonna!), it's not going to bankrupt me or cause my family unnecessary stress down the road.
I spent a lot of work figuring this out with my spreadsheets and after everything had arrived and is put in place, my decision was perfect. Now I just got to get to brewing...
More Walk-in Cooler Work
My dad and I worked on drywalling the outside of it so it didn't look like a giant...cooler...in the middle of the place.
Federal Application Status
This was about the one month mark since my application had been accepted for processing. When I submitted, the Feds must not have fully updated the website as it was running around 90 days average for processing. I called up just to inquire on how things are going and if there were any questions. The lady I spoke with told me it's now 111 days for applications submitted in October. That's nearly a whole extra month. Let's hope it's a 'wide' average and I provided a complete application and there are no issues so I can be below it.
The Federal representative also told me that I was the one thousand, six hundred and fourty-second brewery application to date this year. Wow. Looks like I'm going to be burning through rent and utilities for a little bit longer....it's going to be a cold winter in here...
Next Week
- Finish interior of cooler
- Finish flooring of cooler
- Install the AC unit and Coolbot and hopefully do a test cool.
- Work on the piping for the brewsystem and figure out it's exact location...as then I need to start thinking about the bar.
And thanks too...
Jesse and John for the manpower in helping move the brewsystem and getting up early Sunday to do it. Thanks to my Dad for all of the interior help this week. He's been really putting in the hours, many times when I'm not even there.
-
The Journey
- Building R.Shea Brewing: Week 14, Nov 3-9, 2014 (previous post)
- Building R.Shea Brewing: Week 16, Nov 17-23, 2014 (next post)
We have the perfect party room waiting!
Contact partyroom@rsheabrewing.com and ask about our party space and catering menu... perfect for parties of 40-70 people. And you can’t get any closer to great beer and food!